All Nigeria regulations
NigeriaS.I. No. 15 of 2026 (Official Gazette No. 45, Vol. 113)

Nigeria Upstream Petroleum Decommissioning and Abandonment Regulations, 2026 (with PIA 2021 ss.232-233)

In forceIn force or in effect today.

Made on 9 March 2026; the Regulations revoke the 2023 Regulations, with a savings clause for steps already taken under them.

Summary

Sections 232 and 233 of the Petroleum Industry Act 2021 require every upstream licensee or lessee to plan, fund and carry out decommissioning and abandonment of its facilities. The 2026 Regulations, made by NUPRC, revoke the 2023 Regulations and require a decommissioning fund in US dollars held in escrow for each licence or lease, advance notice before decommissioning, and consultation with host communities.

Key requirements

Maintain a decommissioning and abandonment fund per licence or lease (held fully in Nigeria, or at least 15 per cent in Nigeria for IOC-led joint ventures). Give 12 months' notice before onshore and 60 months' notice before offshore decommissioning. Consult host communities. File annual fund statements with NUPRC and the Nigeria Revenue Service within 90 days of year end. Penalties include USD 500,000 a year for late plans or funding and USD 1,000,000 for unapproved decommissioning; penalties are not cost recoverable.

In force from

9 Mar 2026

Regulator

NUPRC (upstream); NMDPRA (midstream and downstream)

Impact

5/5

Sectors

  • Extractives
  • Energy

Who it affects

  • Oil and Gas
  • Extractives
  • Infrastructure

Sources

Last checked against sources on 2 Nov 2026 Suggest a correction

Research information, not legal advice. Always read the source document and take advice before relying on this summary.