GhanaRenewable Energy Act, 2011 (Act 832), as amended by Renewable Energy (Amendment) Act, 2020 (Act 1045)

Renewable Energy Act, 2011 (Act 832), as amended 2020 (Act 1045)

In forceIn force or in effect today.

Summary

Act 832 established Ghana's renewable energy promotion framework: licensing, the Renewable Energy Fund, renewable purchase obligations and originally feed-in tariffs. The 2020 amendment (Act 1045) shifted procurement to competitive auctions, introduced clearer net-metering arrangements and strengthened the framework for distributed generation. Together with Ghana's Energy Transition Framework (2022) targeting net zero by 2070, the regime defines market access for solar, wind, mini-hydro and waste-to-energy investment. Developers should track Energy Commission licensing codes and auction rounds; commercial users benefit from net metering for rooftop solar. Key changes: 2020: competitive procurement, net metering; Energy Transition and Investment Plan guiding policy since 2022 Practical implications: Bid-based market entry; corporate rooftop solar legally supported via net metering Penalties: Licence sanctions and fines under Energy Commission Act

Key requirements

Licensing for RE generation/commercial activity; renewable energy purchase obligations; net metering rules; local participation expectations Who must comply: Renewable energy developers, utilities, bulk customers, charcoal/biomass commercial actors Reporting: Licence returns to Energy Commission Timeline: Operational; competitive auctions replacing feed-in tariffs since 2020

In force from

31 Dec 2011

Regulator

Energy Commission; PURC

Impact

4/5

Sectors

  • Energy
  • Utilities
  • Manufacturing

Who it affects

  • Energy
  • Utilities
  • Manufacturing